HEALTH FACILITIES COMPLETED PROJECTS
-
Qateef Central Hospital
Employer : KSA Ministry of Health |
Location : Qateef / Saudi Arabia |
Date of Contract : 2014 |
Date of Completion: 2017 |
Closed Area : - |
Qatif Central Hospital was built in 1985. According to the Health Institutions Accreditation Central Board (CBAHI), the hospital is very old, so it's the job of renewing the entire electrical and mechanical system along with the architectural elements. Electromechanical and Construction Works: • Renovation of Hot Water and Cold Water Installations for the Main Hospital Building, • Removal of Wet Volumes and Adjustment of Standards, • Renewal of Lighting Systems and Socket Installations, • Electrical Panels; • Roof Insulation for auxiliary buildings and residential blocks; • Renewal of the Fire Hydrant Line; • Waste Water and Rain Water Lines Pump Stations have been renewed.
-
Dammam Universty PIII
Employer : Dammam Universty |
Location : Dammam / Saudi Arabia |
Contract of Date : 2014 |
Date of Completion: 2015 |
Closed Area : - |
Saudi Arabia – Rainwater Collection Line, Rainwater Drainage Line, Pumping Station Building and Electric Room will be built in the campus areas of Dammam University to collect rain water and discharge it into the sea. Within the scope of Electromechanical and Civil Works: For Rainwater Collection Line: • collection pit • manhole • Dia 400 to Dia 1000 mm GRP pipe; For the Pumping Station Building: • 5 x 400 lt/s submersible pumps •Dia 500 to 1000 mm ductile iron pipes and valves; • For Rain Water Discharge Line: • Dia 1000 mm GRP pipe • 2 discharge chambers • 3 valve chambers; • For the Electric Room: • 1250 kva generator • daily tank • fuel pump system • underground main fuel tank ATS • MCC – ICP – LPP – DDC Panel • fire alarm panel • exhaust fan • damper and motorized fire dampers • FM200 fire extinguishing can be listed systems and main items are equipment. The Capacity of the Project is 5760 m³/hour.
-
King Fahd Hospital
Employer : KSA Ministry of Health |
Location : Al Hassa / Saudi Arabia |
Contract of Date : 2014 |
Date of Completion: 2018 |
Closed Area : - |
Saudi Arabia is still working in Hofuf, which is still working in Hofuf, Renovation of Fahd Hospital has been undertaken. Electromechanical and Construction Works: In Construction Works: • 20 thousand m² Linoleum Floor Covering • 2 thousand m² Ceramic Floor Covering • 25 thousand m² Suspended Ceiling • 1040 Fire Resistant Doors • 10 thousand m² Wall Ceramic • 4 transforming the patient rooms with bed into 2-bed patient rooms • replacement of all hospital Aluminum Windows. Electrical Works: • All Hospital Lighting - Energy Pipes and Cables • Lighting Luminaires • Lighting and Electrical Sockets Replacement. • Low Current Panels • AHU Panels • Electrical Panels and • Transformers replacement. • Replacing the Busbar System. Under Weak Current Systems: • BMS • CCTV • Master Clock • Public Address • Nurse Call • Master Antenna • Data & amp; Telephone • Fire Alarm System. • In Mechanical Works: • Replacement of 4 500-ton Chiller, • Renewing of the Cooling Tower • Cleaning of the entire Ventilation System • Renewing of the Fire Line • Renovation of the equipment of heating and cooling systems • Renovation of Waste Water and Clean Water Pipes • Renewal of Mechanical Rooms.
-
Jubail Central Hospital
Employer : KSA Ministry of Health |
Location : Jubail / Saudi Arabia |
Date of Contract : 2014 |
Date of Completion: 2017 |
Closed Area : - |
Eastern Province city of Saudi Arabia; The renovation works of the Jubail Central Hospital, which is still in service in Jubail, includes the main hospital building, 5 auxiliary buildings and 14 residential blocks. Electromechanical and Construction Works: • Renovation of Hot Water and Cold Water Installations for the Main Hospital Building, • Removal of Wet Volumes and Adjustment of Standards, • Renewal of Lighting Systems and Socket Installations, • Electrical Panels; • Roof Insulation for auxiliary buildings and residential blocks; • Renewal of the Fire Hydrant Line; • Waste Water and Rain Water Lines Pump Stations have been renewed.
-
TSK Hand in Hand Foundation Rehabilitation and Care Center
Employer: Öztaş Construction |
Location : Ankara / Turkey |
Date of Contract : 2007 |
Date of Completion : 2008 |
Closed Area : 30.074 m2 |
TSK Elele Foundation rehabilitation and care center has a closed area of 30.074 m2. The rehabilitation center has a capacity of 250 beds. Mechanical works: • All plumbing works • Heating, cooling and ventilation installations • Fancoil installation • Fire extinguishing systems • Building automation systems.
-
SSK Adapazarı Hospital
Employer: Urban Construction |
Location : Adapazarı / Turkey |
Date of Contract : 2003 |
Date of Completion : 2004 |
Closed Area : 24.000m2 |
SSK Adapazarı Hospital has 24.000 m2 closed area. Within the Electromechanical Works • LV-MV distribution systems • Lighting and power distribution • Fire alarm system • Telephone, data, CCTV, sound systems • Nurse call system • Patient sorting system • Internal communication system • All plumbing works • Heating, cooling and • Fancoil installation • Fire extinguishing systems • Building automation systems.
-
Taganka Hospital
Employer: Urban Construction |
Location : Moskova / Russia |
Date of Contract : 1999 |
Date of Completion : 2001 |
Closed Area : 15.000 m2 |
The hospital has eight floors and has a closed area of 15.000 m². Electromechanical works: • Sanitary and wastewater installations • Heating installations • Ventilation and air-conditioning systems • Pool and hydrotherapy facilities • Smoke extraction systems • Fire protection systems • Rainwater drainage systems • Central hot water galleries piping and mechanical rooms. It was delivered on turnkey basis.
-
SKB Russian Federation Presidential Hospital
Employer: Urban Construction |
Location : Moskova / Russia |
Date of Contract : 1997 |
Date of Completion : 1998 |
Closed Area : 17,000 m2 / 49,500 m2 |
Electromechanical works: Electrical installation and assembly works, Dismantling of old installations in mechanical works, Mechanical installation and installation works. Mechanical works include: • Dismantling of old installations, • Temporary malaria installation, • By-rust lines, • Clean and waste water piping of all patient rooms, • Installation of sanitary and chromatic materials, heating installation and radiator installation, • Ventilation and air conditioning • Hygienic systems, • Smoke evacuation systems, • Fire protection systems, • Rainwater drainage systems, • Central hot water galleries, piping works.
-
Michurinsky Hospital
Employer: Urban Construction |
Location : Moskova / Russia |
Date of Contract : 1997 |
Date of Completion : 1998 |
Closed Area : 10.220 m2 |
The closed area of the hospital is approximately 6,500 m2. The building; • Lighting installation • Strong current installation • Weak current installation • Automation of the building was done by us. The other sections included in the Michurinsky hospital project were done in 3 sections. 1. section • Lighting installation • High current installation • Weak current installation • Automation works are done 2. section: 8th floor intensive care service. Lighting installation • High current installation • Automation works are performed. 3. section: It is the centralization center. In this section; • Lighting installation • Strong current installation • Weak current installation • The automation works have been completed and the administration has been delivered.
-
AU Medical Faculty Ibn-i Sina Hospital
Employer: Universty of Ankara |
Location : Ankara / Turkey |
Date of Contract : 1984 |
Date of Completion : 1985 |
Closed Area : 156,000 m2 |
Ibni-Sina Hospital has 18 floors and has a capacity of 1286 beds. Electrical works: • MV cells installation • 3 1600 kVA 34.5 / 0.4 kV power transformer, secondary protection system • 2 960 KVA diesel generator group project • 210 delegated simultaneous translation facility • Grounding and lightning arrester facility • 16 units of air handling unit works. In 2000, a number of revisions were made at the Ibn-i Sina Hospital. This includes: • Merlin Gerin O.G. • MCC panel connections • A.G. main distribution and transfer boards • Electric floor boards replacement • 2250 kVA CAT diesel generator plant installation.